Write the Assumption Next to the Number
Every estimate rests on assumptions the reader cannot see. Writing the assumption beside the number turns a bare figure into something a reader can question.

A plan shows a single line: "Migration, six weeks." The room accepts it, because six weeks sounds reasonable and nobody wants to be the person who asks. Three weeks in, the estimate has quietly doubled, and nobody can say when the number changed.
The number was never the problem. The estimate rested on assumptions that lived only in the author's head: that the data was clean, that one person could work uninterrupted, that nothing else would land in the same weeks. Written down, those assumptions are discussable. Left invisible, they are discovered.
TLDR
Attach one assumption line to every estimate.
Name what would make the assumption wrong.
Review assumptions when plans drift.
Keep the habit small enough to survive.
Numbers travel without their context
An estimate is a conclusion, and conclusions travel further than their reasoning. "Six weeks" gets quoted in a chat thread, repeated in a meeting and pasted into a plan, and at each step the conditions behind it fall away.
The reader who sees the number three weeks later has no way to know it assumed clean data and a clear calendar. They hold the conclusion with none of the reasoning, and they will plan against it.
One line beside the figure
The fix is deliberately small: when a number appears in a plan, one line beside it names the assumption it depends on. "Six weeks, assuming the export is complete and one person owns the work." Two clauses, written in the time it takes to type the estimate itself.
Government guidance on quality analysis formalizes the same instinct in what it calls an assumptions log: a register that describes each assumption, notes who owns it and records when it was checked. A team plan does not need a formal register. It needs the same sentence, written where the number lives.
Assumptions have a lifespan
An assumption is not a permanent fact. "One person owns the work" is true in November and may stop being true in January, when that person is pulled onto something else. Good practice treats assumptions as dated statements that need the occasional look, not as furniture.
When a plan starts to drift, the assumption line is the first place to look. Often the estimate is still honest and the assumption has quietly expired, which is a much easier conversation than asking why the number was wrong.
An illustrative estimate
A fictional plan line reads: "Move the shared folder, two days. Assumes the current structure is kept and both editors are free Thursday."
A reader can now do three useful things: accept the estimate knowingly, challenge the assumption ("Thursday is the demo rehearsal"), or watch for the assumption breaking. The bare "two days" allowed none of these. The line costs ten seconds and buys all three.
Frequently asked questions
Does every number need an assumption line?
No. Reserve it for estimates people will plan around: durations, dates and capacities. A page count in a draft does not earn one.
What if the assumption is uncertain?
Say so in the same line: "assuming the export is complete - unverified." An honest uncertainty is more useful to the reader than silent confidence.
A practical next step
Find one number in a current plan and add its assumption in a single line. If the line is uncomfortable to write, the number was carrying more than it showed, and the reader needed to know.